主题:大神帮忙解答:P6 中的Activity 与 Step 的区别,回答有奖!!!
回帖:Activity Steps offer several advantages.
One, you can break down a complex activity into a series of, well, steps that better describe the scope of work. The activity name does not need to go into a great deal of detail because the steps offer additional explanation.
Two, it becomes much easier to update a complex activity with steps because rather than trying to come up with a percent complete for the overall task, each step is updated individually, thereby generating an overall percent complete. Have you ever decided that an activity was 37.25% complete? Me neither, but Activity Steps can do that.
Third, Activity Steps do not require logic so it is a great way to track work that cannot easily be sequenced. Let us say there are several air handling units in the building and you have been told that only one will be installed at a time due to the available manpower. But no one knows the order in which the AHUs will be installed. No problem. We can list the AHUs as Activity Steps; the work cannot proceed out-of-sequence since there is no predefined sequence.
下一楼›:step:作业步骤一般是统计作业进度用的,
activity:作业做计划用的
作业步骤是对作业的 ..
‹上一楼:用作业步骤的方法可以减少很多计划更新后的脱序现象,更加减少了逻辑关系的重新调整。
而且 ..