1楼:用作业步骤的方法可以减少很多计划更新后的脱序现象,更加减少了逻辑关系的重新调整。
而且 ..
[
wjwei1990 2017-11-21 18:00]
2楼:Activity Steps offer several advantages.
One, you can break down a complex activity i ..
[
wjwei1990 2017-11-21 20:23]
4楼:wjwei1990:Activity Steps offer several advantages.
One, you can break down a complex ..
[
dallen 2017-11-22 17:27]
5楼:sdgaoke:step:作业步骤一般是统计作业进度用的,
activity:作业做计划用的
作业步骤是 ..
[
dallen 2017-11-22 17:30]
6楼:dallen:if one complex activity have some steps, and the steps have no logic eac ..
[
wjwei1990 2017-11-22 22:19]
7楼:dallen:作业下面的步骤是否可以导出PDF 与作业一起形成甘特图?
对于一些工序之间逻辑性不强 ..
[
sdgaoke 2017-11-23 08:15]
8楼:wjwei1990:No,you can not calculate the duration with the steps method.
You need recor ..
[
dallen 2017-11-30 09:45]
9楼:sdgaoke:第一,作业步骤没有时间的日期属性,无法生成甘特图,且步骤与作业很难打印在同一个页面 ..
[
dallen 2017-11-30 09:47]